Istanbul Airport (IST) - the city’s newest hub – will open its third parallel runway today, June 14th. The airport, set to become the World’s Biggest by the time of completion, will have a total of six runways by 2028.According to Anadolu Agency (AA), Turkey’s President Recep Tayyip Erdoğan will commemorate the opening of the runway in a ceremony today.Istanbul’s newest airport opened its doors for a soft launch in October 2018 and proceeded to become fully operational in April 2019. However, in the first year since 2018, the airport had already managed to welcome over 40 million passengers. The airport aims to hit 200 million passengers annually by the time it is fully complete.

Opening a new parallel runway

The new parallel runway is located east of IST’s terminal – and will be ready for flight operations by June 18th. Further, the new runway is IST’s third and will enable simultaneous take-offs and landings.

This triple parallel runway capability will allow Istanbul Airport to join the ranks of a small number of hubs. Such operations are only available at a few airports worldwide, including Amsterdam Airport Schipol, Kuala Lumpur International Airport, and Chicago’s O’Hare International.

AA reported that the new runway would also make for more efficient taxi times and increased landing capacity.

“The landing capacity will rise by 50% and taxi times will also drop by half after the opening of the new runway,” Turkish Transportation and Infrastructure Minister, Adil Karaismailoglu, mentioned.

Istanbul Airport Runway
The latest runway will allow take-offs and landings to occur concurrently. Photo: Istanbul Airport

In a statement seen by Simple Flying, the new runway will reduce landing time from 15 to 11 minutes. The average take-off time will decrease seven minutes from its original of 22 minutes.

Additionally, air traffic capacity will rise from 80 plane landing/take-offs to at least 120. The runway will also improve the slot flexibility of carriers.

According to Kadri Samsunlu, CEO and General Manager of iGA Airport,

“This has been a difficult year for the aviation industry, but we see this compulsory break as an opportunity to maximize the passengers’ travel experience at Istanbul Airport. We expect the stagnation we have been experiencing for the last couple of months to resolve very soon. Our new runway will be immensely helpful in that sense.”

To date, this brings IST’s total operational runways to five, out of which three are independent.

Four-phase journey to completion

The four phases of IST started with its main terminal that opened in 2018, followed by a second terminal, and three independent runways. According to Airport Technology, the opening of a fourth runway will mark the debut of phase two – which will end once three parallel taxiways are complete.

Phase three will see the addition of a 500,000m2 passenger terminal, one runway, and taxiways. The final stage includes the addition of a runway, parallel taxiways, and a 340,000m2 terminal.

Istanbul Airport Four Stages
There will be 200 million passengers passing through IST annually once complete. Photo: Istanbul Airport

The airport prides itself as a hub connecting Asia, Africa, and Europe. Operating from a domestic and international terminal, IST aims to perform up to 2,000 flights daily once complete. As aforementioned, the goal is to hit 200 million passengers per year after 2028, the predicted completion year.

A bumpy ride for Istanbul Airport

It was not all smooth sailing for Turkey’s newest airport. Initially, the airport was supposed to become fully operational in 2018, which is now known as its soft launch.

The airport delayed its launch multiple times due to the new airport “not being prepared to receive all flights” before finally opening gates on April 6th, 2019.

Istanbul Airport Fog issues
Fog issues plagued the new airport back in May 2019. Photo: Istanbul Airport

Even after opening in 2019, the mega-hub experienced fog issues. Fog is nothing unfamiliar to residents of Istanbul, which arrives by way of Russia’s cold air crossing the Black Sea. Such fog shielded Istanbul’s old Ataturk Airport due to its location on the southern coast. However, IST’s position makes it vulnerable.

Hence, multiple flights had to be diverted to another base when fog hit Istanbul in May 2019. An issue that is too late to be fully solved, random bouts of fog might end up affecting IST’s operations.

What do you think of Istanbul Airport’s quick expansion? Have you visited the airport yet? Let us know in the comments.